| 1.
Earth work excavation for the clearance of debris
without disturbing the members to a width of 5
M to 9M all-round Garbhagriha & mahamantapa upto
a depth original working level by taking full
care not to disturb / cause any damage to the
structural members/ which may found inside the
debris and stacking or such members found during
the course of clearance work at a suitable safe
place for re using/ refixing them in its original
position and bring the entire surrounding area
neat and throwing the debris beyond 100M from
the temple and formed neatly. 2. Numbering of
structural members with suitable colours clearly
both inside as well as outside mentioning clearly
direction of courses etc. so that there should
not be any difficulty or confirm while putting
them back to its original position.
3. Providing propose suitably to the structural
members which have disturbed ( leaving ) all-round
garbhagriha using casuarinas poles etc. as a precautionary
measure for taking up the dismantling work.
4. Dismantling of bulged out & over hanging structural
members such as heavy roof slabs, heavy chejjas
(eave) pillars along with inner veneer slabs &
core filling and bricking them down carefully
without damaging using puller block etc. and neatly
stacked number wise on the respective sides.
5. Strengthening foundation by filling granite
random rubble ranging from 40 cm. to 15cm. size
mixed with pebbly sand in layers gaps/ voids neatly
packed with chips well and consolidated including
watering heavily and finished neatly.
6. Laying cement concrete 1:4:8 proportion over
the bubble filling using 40nim size granite jelly
Including watering consolidation curing etc. complete
7. Restoration of dismantled structural members
in their proper position and in original level
carefully, filling the core with brick jelly mixed
with lime mortar 1:4 proportion and well consolidated
the joints or members are pointed with 1:4 proportion
of CM on their back side, fixing of stainless
steel dowels ( l5cm x 20cm x 4mm) for each member
for keeping firm in their position each member
by taking all care and precautionary measures
and finished as per original complete.
8 Watering tightening the terrace ( roof) by laying
15 cm. ( average) thick W.P.C. using one of burnt
lime and three of brick jelly of 25mm to 40mm
size laid in proper slope including packing the
joints or roof slabs with chips and 1:4 cm. well
consolidated and top plastered with 20mm thick
1:1:6 combination mortar including joining curing
etc. complete 18 sqm.
9. Provision for the replacement of broken or
mixing roof slabs beams capitals found during
the execution and fixing in conformity as per
original.
10. Laying flag stone pavement using 10cm. thick
stone slab neatly 2 line dressed including sunk
pointing with 1;3 CM toning curing etc. complete.
|