STRUCTURAL WORKS
Removal of wild grown grass and
vegetation over the roof top along with roots
without disturbing the existing remnants of brick
structure carefully, using proper scaffolding
and disposing the same away from the temple premises
completely. Removal of earth existing over the
roof of temple carefully without disturbing the
brick remnants in their places in order to reproduce
the same again on the temple by providing suitable
supports to the intact structure as a precautionary
measure to avoid falling from their positions
and disposing the debris beyond temple premises
as per direction of officer incharge of work during
the time of execution and finished neatly.
Scientific clearance of filled
up earth in the court yard in order to expose
the hidden temple adhistana mouldings without
causing any damage to the structural parts during
clearance work simultaneously restore the original
temple height as well as to bring back the original
working level and disposing the excavated debris
through check up and document any valuables found
inside the debris if found and finished neatly.
Earthwork excavation hard soil all round temple
structure carefully by providing props to the
structures as a precautionary measure in order
to avoid sudden slipping of members during excavation
in process, disposing of the excavated stuff as
per direction of officer incharge of work and
finished neatly. Laying 1:5:10 cement concrete
in foundation using good quality 40 to 50 mm size
hard jelly neatly laid consolidated including
curing complete.
Strengthening the foundation
of temple walls by under pining by using stones
in 1:6 cement mortar (as far as possible with
lengthy stones) by taking all care and packing
the gaps in trench fully (preferably using hammer
packing) and finished neatly, including filling
the trench with available earth watering consolidation
etc., completing any sort of gaps. Finally finishing
the work as per direction during excavation. Dismantling
the accretionary mud wall in order to retain the
original Features of temple entrances and finished
neatly. Dismantling the disturbed parts walls
disturbed from their original level (bulged stones)
after numbering them carefully finished.
Restoration of dismantled structural
members (ie., item No. 8) as per original style
in their proper places by providing MS dowels
in concealed manner and filling the core with
proper material as required during work with proper
scaffolding etc., complete. Lifting the sunken
pillars in Navaranga using proper jacks and putting
sand bag supports below the roof slabs and packing
below the pillars suitably and bring them to original
level. Provision for preparing and fixing of structural
members which came across during the process of
execution which could not be anticipated while
preparing the estimate. Providing and fixing temple
type door shutters using 2" thick (5 cm thick)
plank on back portion and using good quality Nandi
or any other local variety preferably termite
resisting quality scantlings of 7 cm x 13 cm size
with carving of flowers in the panels with all
old type temple type fixture specially prepared
for order including 2 coats of touch wood painting
etc., complete.
Providing and fixing grill work
for the openings using 40 mm x 40 mm x 6 mm MS
angle frame work for further details such as flowers
and partitions using 25 mm x 4 mm flats neatly
cut welded grinded with hold fast and fixed in
position as per direction firmly with 2 coats
approved quality paint over a coat of primer paint
complete. Dismantling the sunken floor slabs after
preparing its sketch and numbering in order to
replace them in their places back and replacing
the broken ones with fresh one's neatly dressed
to match with original surface of flooring laid
in proper level over a sand bed of 8 cm to 10
cm thick and joints sunk pointed with 1:3 CM and
toned curing etc., complete. Laying weather proof
course over the Navaranga roof only by cleaning
roof slab joints thoroughly using proper tools
grouting the said joints with 1:3 CM mixed with
WPC neatly and laying brick jelly in lime 1:3
proportion laid in layers not exceeding 15 cm
at a time, consolidated thoroughly, the top most
layers rammed with wooden beater by sprinkling
lime water and top plastered with 1:6 CM to a
thickness of 20 mm by mixing W.P.C. and toned
and curing etc., complete.
Laying flag stone pavement all-round
the temple using 10 cm thick slabs of Hanumana
Matti quarry neatly 2 line dressed for the top
of the surface sides trimmed laid in proper level
over sand cushion of 8 to 10 cm thick with necessary
earth work and finished neatly. Sunk pointing
the structure joints and floor slabs etc., by
raking joints 30 nun deep and then pointed with
1:3 CM neatly filled and toned to match the structure
and finished neatly. Providing and fixing MS chains
on either side and on the front side of the beautifully
and elegantly decorated Nandi using proper MS
flat verticals fixed in the ground without Mating
the esthetic view of temple for safety of Nandi.
SHIKARA AND HARA WORKS
:
Reconstruction of all the missing
shikara's by preparing drawings of remnants of
brick work existing at site such as Karna Kutas
Panjara and Shala, which are found at few places
in a highly damaged condition preparing proposed
shikara by developing basing on the remnants in
consultation with advisor and also traditional
stapaties by preparing/ Manufacturing bricks of
various shapes as existing at site by engaging
skilled artisan and burnt to the texture of old
brick to have uniformity and constructed using
well ground 1:2 Lime mortar using traditional
ingredients such as gum. Egg, Balefruit, Jaggery
and Barks of tree like Neem etc. and plaster with
lime mortar including smooth and fine rendering
etc. complete. Reconstruction of Hara portion
as original ones as per details mentioned under
item No. B 1 and finished neatly.
GADDIGE
Dismantling the modem structure
constructed for the Gaddige which does not match
with the temple structure and providing a simple
and matching structure with stone platform measuring
7m x 2m x 60 cm with stone pillars of 20 cm x
20 cm x 1.5m Ugh neatly dressed and covered with
gray colour sheet on top ltd finished neatly.
CLEANING OF STRUCTURES
Provision for cleaning of the
temple structure both inside and outside top to
bottom the doors jambs Toranas and ceilings are
of highly ornamented one now completely covered
with black soot, dust and oily contents etc.,
in consultation with proper chemist and bring
the structure in to original condition for the
benefit of devotees, tourist etc.
RETAINING WALL ETC :
Construction of retaining wall
using random rubble in mud mortar as being in
force at present locally to the sides of earth
from sliding and joints are rack out and sunk
pointed in 1:3 CM and finished neatly. Providing
fixing MS grill Gate using 50 mm x 50 mm x 6 nun
MS angle frame works all round and MS flats of
50 mm x 4 mm for partition and suitable flats
for designs neatly cut welded and grinded and
fixed in position including hold fasts pivots
locking arrangements stoppers with 2 coats of
approved quality paint over a coat of primer paint
etc. complete.
ENVIRONMENTAL DEVELOPMENTAL
WORKS :
Provision for developing the
surrounding temple premises by growing light and
dwarf variety permanent flower plants along with
same seasonal flowers and providing 2 to 3 benches
for visitors to sit and a drinking water facility
in the premises and supply of manure for plants
etc complete. ; (If proposal is accepted details
will be worked out before execution)
|