| PART
A : Major Structural Repairs
Item No. 1 : Rank vegetation
and wild grass has grown over the entire temple
roof since it is being allowed to grow their roots
have penetrated deep in to the structure and caused
damages not only to the roof portion also to the
structures below. It roots might have gone up
to the original foundation courses. Provision
has been made in this item for the removal of
vegetation as for as possible with its roots.
Item No. 2 : As mentioned in the inspection notes
the roof has been dumped with huge quantities
of earth for preventing leakage. This item provides
for removal of debris completely without disturbing
the roof slabs of brick structures. The same on
the cells portion will not the attended.
Item No. 3 : Long back the entire court yard has
been filled with earth. The reasons are not known.
After observing some disturbance of structure
the above action has been done it is purely an
assumption. By filling the original 3 to 4 Adhistana
mouldings are completely covered. Now only 2 courses
are visible. This item provides for the removal
of filled up earth in order to expose the entire
Adhistana mouldings and maintain the original
working level of the temple. By this action the
original height of temple is clearly visible.
Further clearance of debris will be done in the
scientific manner under supervision of officer
that there may exist some archeological valuables.
Item No. 4 to 6 : Trial pits put at 2 places has
shown that foundation of temple structure need
to be strengthened by under pining. Provisions
are made under the said items for removal of earth
slowly below the structure carefully by scoping,
by providing props laying of 1:5:10 CC to a thickness
of 15 cm and over that provide stone masonry using
1:6 CM. While attending the said work all care
will be taken not to allow any gap in between
original courses and the present masonry by packing
the gaps neatly so that there should not be any
rest of disturbance of structure.
Item No. 7 : The temple has two entrances on North
and southern sides originally. The Navaranga was
open one. But the same has been closed by constructing
accreationary mud wall over the Kakshasanas. This
item provides for removal of the said mud wall
and retain the original features of temple.
Item No. 8 to 9 : Two portions of original wall
have completely disturbed and need urgent attention
and proper rectification. Provisions are made
in these items for the removal of parts disturbed
wall and restore them as per original style respectively.
Item No. 10 : During inspection it was noticed
that pillars of Navaranga central bay have sunk
considerably. As suggested in the inspection notes,
attempts will be made to rise them to its original
level by using proper jacks and providing sand
bag supports to the adjoining members. During
execution if another pillars need any attention
/ rectification the same will also be attended.
All these are covered in this item.
Item No. 11 : During inspection of temple in connection
with the preparation of estimate we have not noticed
any breakage of structural members such as beams
capitals roof slabs etc., as inside temple is
very dark and coated with thick dust etc. As per
the experience had in these 9 years of work in
this trust we are coming across the replacement
of broken ones which could be noticed during execution
time only. Keeping this point in mind a token
provision has been provided in this item for replacing
the damaged ones, if we come to know of it during
the execution time. If such things does not occur
this will be savings and will not be incurred.
Item No. 12. : The existing door shutters are
in very bad condition needs urgent replacement
similarly other cells too need door shutters for
safety purpose. This item provides for providing
6 temple type door shutters using Nandi or any
other local quality wood and apply two coats of
touch wood paint etc.
Item No. 13 : Provision has been made in this
item for fixing MS grills for safety of sculptures
available in this temple. Since we have removed
the mud wall from the structure (vide Item No.
7).
Item No. 14 : Flooring slabs of cells, Antarala
and Navaranga have not only sunk and also developed
several cracks. Provision has been made to remove
the most damaged slabs from the area & replace
with suitable slabs neatly dressed in order to
match the old floor slabs and laid over a sand
cushion of 8 to 10 cm thick in proper level.
Item No. 15 : This item provides for water tightening
the roof portion of Navaranga only, after grouting
the joints of roof slabs with 1:3 CM. Since the
ceiling is of stepped type that is criss cross
type provision has been made to lay the same material
and bring the surface to a level before laying
W.PC. Further the Hara courses are quite high
provision is also covered to lay W.P.C. to suit
its level and provision is also made to plaster
the top surface with 1:6 CM to a thickness of
20 mm.
Item No. 16 : In order to strengthen the foundation
of wall we have excavated earth all-round the
temple and refilled after the work is over. To
prevent seepage of storm water in to foundation
during the rainy season it is proposed to lay
flag stone payment to a width of 1.5 meter wide
lay on sand cushion of 8 to 10 cm and finished
neatly all these are covered in this item.
Item No. 17 : This item is self explanatory which
provides for grouting the joints of walls and
pointing the joints of flag stone pavements and
floor slabs etc.
Item No. 18 : In the Navaranga beautiful Nandi
is available. To avoid the people coming near
to it and cause any damage etc a crude and ugly
wooden railing is fixed on three sides. This item
provides for replacing the same with a chain without
marring the esthetic view of temple.
B. SHIKARA AND HARA WORKS
:
Item No. 1 and 2 : The inspection
note clearly indicate the prevailing condition
of Shikaras and Haras. Only 2-3 pieces of brick
works are available that too in a very alarming
manner. Existing ones gives some clue of Karna
Kutas Panjaras and Hara part especially on the
northern side of Sri Basaveswara Temple. Top courses
over the said one are completely missing. Instead
only mud heap is available. Further existing brickwork
over surya shrine gives some idea of courses existing
originally. And in consultation with archaeologist
we have to develop the shikara drawing for the
proposed one only if it is okayed by archaeologist
we have to attend there execution. As per suggestion
of archaeologist we have to manufacture bricks
of the same type of brick for reconstruction.
Here it is to be noticed that no bricks are cut
to shape. Instead moulded bricks are used through
out. We have here nearly 6 to 8 different variety
of moulded bricks and we have to prepare them
accordingly. Further as suggested we have to prepare
a lime mortar in traditional style using ingredients
such as Jaggery Bale fruit, gum etc and prepare
a lime paste. For this purpose either we have
to prepare mortar grinding mill and grinding stone
or to go in for diesel mortar grinder, which is
not easy. Since this is a unique structure as
mentioned by archaeologist we may take pain and
try our best in reconstructing the shikara. Further,
archaeologist during the time of inspection has
informed such type of shikara in stone is available
at Hirehadagali. As such efforts are quite essential
to visit the said temple have the photographs
before finalizing the shikara drawing. Keeping
these facts in mind for estimate purpose only,
token provisions are made for undertaking the
work. After the shapes are finalized, proper estimate
will be framed and sanction will be sought from
Hon'ble chairman.
C. Gaddige :
A modern brick structure has
been constructed few decades back for a yogi /
Jangama/ st. which is not clear. The said structure
is an eye sore and is abutting temple wall. Now
it was programmed to transplant the samadi to
suitable place from the existing spot in order
to keep the temple free from any other structure
near by. Since the villages are reluctant to the
shifting, to avid unpleasant atmosphere with locals,
now it is programmed to minimize the structure
to a size of 2 m x 2m sq platform and to have
a simple canopy over it for which provision is
made in this item.
D. Cleaning of Structures
:
Interior parts of temple cells,
walls, door jams are covered with very layer of
oily matter / soot / dust etc covering the architectural
details having repaired the entire temple fully
it is programmed to clean the above items with
cleaning materials and bring the originality back.
Before doing the work, opinion of proper and experienced
chemist will be obtained. According to his guidance
the cleaning work will be executed.
E. Retaining Wall etc
:
In order to expose the hidden
Adhistana mouldings of the temple and also to
maintain original working level entire court yard
has been lowered by 80 cm. After clearance of
specified area the rest are liable for slipping.
Apart from the above there is possibility of storm
water entering the court yard. To avoid it is
proposed to construct retaining wall to the side,
and rise it, above the adjoining ground, avoid
the flow of storm water in to the temple premises.
F. Environment Development
:
On the western side of the temple,
there are 2 big and small house belonging to the
private party. As soon as we enter the village
there exist vast open ground. In between the ground
and temple these buildings mentioned are constructed.
Unless one goes near the temple one cannot be
able to see the existence of beautiful temple.
Similarly on south west side of temple a small
house and cattle shed is also available. According
to temple committee president, negotiations are
going on with the owners of buildings to hand
over them to temple for improving the environment
and to give a face lift to temple area. Committee
has agreed in principle that they will dismantle
the buildings as soon as they are handed to committee
by the owners and also agreed not to remove the
trees available in the temple premises. Since
we have taken up the work in large scale it will
be good that environment is given a face lift
such as growing dwarf flower plants, few seasonal
flower beds 2 to 3 benches and drinking water
facilities through out by constructing a water
tank. All these are covered under this item.
G. Purchase of Tools
:
For the proper execution of work
purchase of scaffolding materials like poles.,
plank ropes, minor tools etc required. A site
supervisor will be kept for supervision till all
the works are completed in temple. Photo and documentation
of works before, during and after the works are
very essential. During execution the same has
to be visited by the officers for which vehicle
is to be engaged. All these items are covered
in this estimate. Basing on the details furnished
above sanction may please be accorded for taking
up the execution.
|