| Repair
Work of the Main Temple.
Retaining the deities
in worship even during the renovation work is
under progress: - At present, the temple
worship is being performed regularly. According
to information available, the temple authorities
may not shift their deities from their position.
Apart from this, the inner wall is not disturbed
from the original position. For keeping them in
safe condition it is proposed to provide sand
bag and pole support upto ceiling level so that
the worship can also be performed as usual without
any disturbance of renovation work.
Numbering, designing
and coloring of the members for Dismantling Process:
- Provision is made for numbering; preparing
rough sketches of temples etc. are covered in
connection with dismantling
Clearing the Vegetation
Growth: - The courtyard of the temple
has been ploughed for agricultural purposes some
time back. As such, the ground is not so leveled.
Also raw vegetation is grown. In order to clear
the vegetation and level the ground for storing
dismantled members, lump sum provision is made.
Dismantling Parapet Wall
& external Structures of the Main Temple: -
These items provide for dismantling of parapet
wall and dismantling of outer veneer slab from
top to bottom along with care using the pulley
etc., and to stack them in the sides in order.
Excavation Work: -
Provision are in these items for attending Excavation
work below the wall abound to a width 6'-6' by
providing support to wall and lay fresh concrete
below and over its construction size stone masonry
in 1.6cm as there is no proper foundation previously.
Dismantling External Structures
- At present it is observed that few members have
been so damaged that they have to be replaced
with the newer ones. Since it is possible to know
how many members have to be replaced, only after
dismantling exact portion, a lump sum provision
is made. Restoration of Dismantled Members into
their Original Positions: - Provision for restoration
of dismantled members as per original manner.
While doing so, it is proposed to fix M.S. dowels
for each member, in concealed manner. The case
will be filled with brick jelly concrete in steady
mud filling. In between joints, very thin layer
of cement mortar will be used as a binding material
and after entire work is completed, the joints
will be raked, sank painted with 1:3cm
Removing all Covered
materials and Exposing the Shikara after Renovation:
- The Shikara courses are applied with
cement plaster from top to bottom. Now it is not
possible to know how many courses are in the shikara.
Then all the decorated features of stone shikara
are to be exposed as per original condition. Here
also some stones might have been damaged while
plastering. After raking plaster, the joints will
be grouted well and sunk pointed with cement mortar
in 3 proportions mixed with W.P compound and toned
to surface stone. Repair &
Replacement of all Doors,
Fasteners and other accessories: - Condition
of door shutters is not in good condition. Some
part or planks are to be replaced keeping the
safety of sculptures inside. Provisions are made
for replacing wood and to completely change the
fixture, which are very essential.
Construction & Painting
of Parapet wall all-round the Terrace: -
Construction of parapet as per original by using
old bricks stacked. If the better quantity are
not possible to cover the entire parapet, fresh
bricks will be purchased and complete the parapet.
After constructing the entire terrace, it will
be plastered with fresh mortar.
Dismantling of Sunken
Floors and leveling the same after repair: -
Flooring inside temple is undertaken. It is proposed
to lay the same at proper level, over sand cushion
and point the joints. But dressing of slabs etc.
are not proposed and laid as it is.
PART B-- WORKS PROPOSED
IN HADINARU CHAVADI
Numbering, coloring and
repair of all structural Members : -
As stated in part A, the condition of hadinaru
mukhada mantapa has to be attended here also.
At present, sides are leaning heavily. The condition
of cell where chief is supposed to sit and conduct
Royal Durbar is in very damaging condition. Here
the entire Mantapa has to be dismantled and foundation
to be strengthened as done in the main temple
and restore the dismantled members in its original
style. The nature of walls is similar to the one
carried to Main temple, will be followed here
also.
The provision is made for laying
fresh weatherproof course using brick and lime
and the top to be plastered before laying the
joints or once the ceiling will be grouted well.
Provision has been made by us for the item to
dismantle the flooring and relay over a sand bed
[without dressing] and point the joints 1:3 cement
mortars. It was observed while collecting data
for preparing estimate; the storm water was entering
into foundation and caused the damage to the structure
apart from weak foundation. In order to keep the
structure in sound condition after attending the
restoration works, we have planned to lay flap
stone pavement to a width of 5' for entire temple
and Mantapa with fresh slabs, and joints are pointed
with cement mortar. Further the court yard will
be leveled in such a manner that the storm water
will not come towards the structure and even the
water coming from terrace will flow away immediately
from the surrounding. No provision is made for
dressing of slabs. They will be trimmed and laid
in proper level.
PART C - CHEMICAL WORKS
The inner part of the temple
such as doorjambs, ceiling, lathe turned pillars
of the main temple, highly ornamented / decorated
ceilings of Mantapa pillars are covered with either
thick coat of lime wash or black salt or bats
dropping etc. Now we can see only lime wash. It
is proposed to remove them completely using chemicals.
Lump sum provisions are made for the purchase
of materials. The outer surface of temple and
Mantapa are covered with mud and other factors.
Provision has given to wash them completely with
the detergent so that the temple will be free
from the thick coat of material and original feature
is clearly visible for public.
PART D: - MISCELLANEOUS
EXPENSES
For executing the Excavation
work, some scaffolding equipments like Manila
Rope, buckets, etc., are being used. Provision
is made to have photographic documentation and
video shooting at the appropriate time for record
purpose. Provision for fixing direction board,
historical background, board is made. Provision
is made for mending of tools during execution,
keep a hired work site supervisor or store room
for keeping the materials in safe condition and
for transporting the materials from site to other
place for attending repairs if needed. Provision
for conveyance of visiting officers for inspecting
work. Since the work is heavy and troublesome
type, it is proposed to keep some medical facility
at site.
Provisions for the items, which are to be attended
& do not find place in the estimate.
|