Major Structural Repairs

Provision for dismantling the stone members of the shikara with sukanasi, true and false roof, beams, capitals, pillars etc very carefully without causing any damage to the stone members with the help of chain pulley block and derrick pole after proper numbering and documentation and stacking the stone members upto a lead of 20 m etc. complete Provision for laying rubble stone cushion below the flooring not less than 15 cm in size in two layers including watering ramming for proper consolidation, filling sand for the voids (joints) etc. complete. Provision for fixing new stone beams, roof slabs and capital of schist stone in place of broken ones including three line dressing as per original etc. complete.

Provision for reconstruction of the dismantled stone members, very carefully without causing any damage to the stone members with the help of chain pulley block and derrick pole using cement slurry for the fine joints including erection and dismantling of scaffolding, curing etc. complete. Provision for cement pointing 1:3 including grouting for the joints of the double roof over which Epoxy Resin putty pointing upto a depth of 1 cm to prevent leakage of rain water including erection and dismantling of scaffolding etc. complete. Provision for dismantling and resetting the existing undulated flooring around the temple or a sand bed of 5 cm thickness including dressing the ground wherever required with outward slope for easy flow of rainwater including recess/sunk pointing with 1:4 cement mortar for the joints mixed with colour oxides to match with the stone colour curing etc. complete.

Provision for providing new flooring with schist stone slabs from Hanamanahatty quarry (near Ranebennur) 7-10 cm thickness, two line dressed on sand bedding 5cm thick including sunk/recess cement pointing 1:4 mix mixed with colour oxides to match with the stone colour, curing etc. complete. Provision for fixing new wooden doors of ancient pattern with Nandi/Sal wood with 2" thick planks on the back side with styles 4"x2" vertically and horizontally with decorative floral designs in the squares and styles including polishing and fixing with revolving arrangements, brass aldrop for locking arrangements, decorative brass knobs with wood paint/varnish two coats over one coat of primer etc. complete.

Chemical Preservation:

Provision for cleaning the shikhara and wall portions of garbhagriha outside and Adisthana of the temple to remove the lichen and moss and micro vegetational growth by chemical treatment including application of fungicide to the outer walls to prevent future growth application of final preservatives including erection and dismantling of scaffolding etc. complete.

Environmental Work:

Provision for leveling the area on the Eastern side and throwing away the excavated earth upto a lead of 25 m on head load etc. complete. [The work has to be carried out carefully as we are likely to get some members and antiquities in that area]. Provision for construction of dwarf enclosure wall (compound wall) around the temple including excavation for foundation. Laying cement concrete 1:4:8 mix bed for foundation, construction of random rubble masonry for foundation in cement mortar 1:6 mix, construction of size stone masonry in cement mortar 1:6 mix above ground level and laying D.P.C 1:3:6 including finishing for the exposed surface, curing etc. complete. Provision for fixing chain link mesh of 8 gauge 5x5 cm size welded to angle iron frame of size 25x25x5 mm 2.00x1.20m frame fixed to angle iron posts of size 45x45x6 mm 2.20 m high @ every 2 m apart with bottom split and bent above the dwarf compound wall including painting with two coat of anticorrosive paint over one coat of primer etc. complete.

Provision for transposition of various materials from Sirsi/Bangalore and tools & plants, implements etc from other works spots etc. complete. [Note: Lump sum provision is made- for estimation purpose] Provision for engaging a site supervisor for supervision of conservation work, keeping accounts of materials, a supervisor for chemical preservation work [preferably a B.Sc. chemistry] for preparation of solvents etc. traveling expenses of site supervisor Engineers, consultant chemist including consultancy charges, night watchman for safety of materials at site etc. complete.

Rate Analysis:

Dismantling the stone members of the shikhara with sukanasi, true and false roof beams, capital, pillars etc. very carefully without causing any damage to the stone members with the help of chain pulley block and derrick pole after proper numbering and documentation and stacking the stone members upto a lead of 20 m etc. complete. Laying rubble stone cushion below the flooring in two layers not less than 15 cm in size including watering, ramming for consolidation, filling sand for the voids (joints) etc. complete. Fixing new stone beams, roof slabs and capitals of schist stone in place of broken ones from Hanamanahatty quarry lead 120 km original etc. complete.

Provision for reconstruction of the dismantled stone members, very carefully without causing any damage to the stone members with the help of chain pulley block and derrick pole using cement slurry for the fine joints including erection and dismantling of scaffolding material, curing etc. complete. Details as above Construction of plinth portion in cement mortar 1:6 mix, etc. Complete. Cement pointing 1:3 mix including grouting for the joints of the double roof over which Epoxy resin putty pointing upto a depth of 1 cm to prevent leakage of rain water and erection and dismantling of scaffolding etc. complete. Provision for dismantling and resetting the existing undulated flooring around the temple on a sand bed of 5 cm thickness including dressing the ground wherever required with outward slope for easy flow of rain water including recess/sunk pointing with 1:4 mix cement mortar for the joints mixed with colour oxides to match with the stone colour curing etc. complete.

Fixing new stone flooring with schist stone for Hamanahatty quarry 7 to 10 cm thickness two line dressed on sand bedding 5 cm thickness including Sunk/Recess cement pointing 1:4 mix, mixed with colour oxides to match with the adjacent curing etc. complete. Fixing new wooden doors of ancient pattern with nandi/sal wood with 2" thick planks on back side with styles 4"x2" vertically and Horizontally with decorative floral designs in squares and styles including polishing and fixing with revolving arrangement, decorative brass knobs with washers, nut bolts and pointing with wood paint/varnish two coat over one coat of primer etc. complete. Leveling the area very carefully and throwing the excavated stuff upto a lead of 20 m on head load (as we are likely to get fallen stone members and antiquities) etc. complete.

Cleaning the shikhara, garbhagriha outer walls, adhistana of the temple to remove the lichen and moss and micro vegetational growth by chemical treatment including application of fungicide to the outer surface to prevent future growth and application of final coat of preservative including erection and dismantling of scaffolding etc. complete. Construction of dwarf enclosure wall (Compound wall) around the temple including excavation for foundation, laying cement concrete 1:4:8 mix bed for foundation, construction of random rubble masonry for foundation in cement mortar 1:6 mix construction of size stone masonry in cement mortar 1:6 mix above G. L and laying DPC 1:3:6 mix including finishing for the exposed surface curing etc. complete. Fixing the chain link mesh of 8 gauge 5x5 cm size welded to angle iron frame of size 25x25x5 mm 2.00x1.20 m frame fixed to angle iron posts of size 45x45x6 mm 2.20 m high @ every 2m apart with bottom split and bent fixing over dwarf compound wall including painting with two coats of anticorrosive paint over one coat of primer etc. complete.


 

 